This project started in November 2010. Once commissioned, our four small hydropower plants in Bosnia and Herzegovina (including the Mujada facility already in service), will result an aggregate installed capacity in excess of 5 megawatts. A number of permits has meanwhile been granted, in particular for Poljanice 1. However, due to the extremely slow approval procedures, some permits are still pending at all three sites. A conclusion of these protracted procedures is still not in sight.